How to apply microtopping, step by step

From substrate to varnish: 4 to 5 days on site, 7 days before normal use.

Yellostone microtopping, often called microcement, is ready to use: no powder to mix, and it does not dry out in the tub, so you have time to work. A careful DIYer can apply it themselves. This guide follows our application datasheet, which you can download from the kit page.

Before you start

  • Do a test on a board or a sample: you will get your technique right before the real job.
  • Ventilate or heat: a fan or a site heater speeds up the drying of the microtopping and the varnish.
  • Allow the time: 4 to 5 days to apply, then 7 days before normal use.

The equipment

  • A sander, abrasives in 40/60, 60 and 120 grit, and a vacuum cleaner.
  • A roller for the primer and the varnish.
  • A trowel or a spatula for the two A coats.
  • A plastic smoothing spatula for the B coat.
  • A paint mixer to blend the varnish with its hardener.

1. Prepare the substrate

Sand the substrate with 60 grit, then vacuum. Over tiles, first fill the grout lines with a skim to zero, using a ready-to-use tile adhesive: otherwise they show through (see microtopping over tiles). On underfloor heating, switch the screed on for 24 h before you start.

2. Apply the primer

Roll on the bonding primer at 100 to 120 g per m². It dries in 2 to 8 h depending on the substrate.

3. First A coat

Mix the A tubs to even out the texture and the colour. Spread about half of the A tubs with a trowel or a spatula, 1 mm thick (about 1 kg/m²). This coat does not affect the final look. It hardens in 2 to 6 h: a visual check is enough.

Then lightly sand with 40/60 grit, just to knock off any excessive ridges, and vacuum.

4. Second A coat

Apply the rest of the A tubs with random strokes, aiming for a fairly smooth result. This stroke creates the final effect: grained, shaded or more textured. Sand as for the first coat, keeping slight reliefs: heavy sanding wipes out the material effects.

5. The B coat, the finish

Mix the B tubs; if the product is too thick, add a little water. Work it with a plastic smoothing spatula, pressing and scraping the coat to fill the hollows left by the A coat. After 12 to 24 h of drying, sand lightly with 120 grit, then vacuum thoroughly.

Wait 24 h before applying the varnish.

6. Two coats of varnish

Filter the varnish, then mix it with its pre-measured hardener for 1 minute with the mixer: a poorly blended mix is less resistant. The mix must be used within 30 minutes.

  • Matt finish: two coats by roller, 3 to 24 h apart. The milky look disappears as it dries; even out any white overlaps.
  • Satin finish: one impregnation coat, on a floor above 12 °C, then the satin varnish the same day, 1 to 4 h later. A second coat of varnish is recommended in a shower or on a worktop.

Drying

After 24 h, the microtopping is still fragile: it hardens in contact with the air for at least 7 days.

  • Do not cover the surface (tarpaulin, cardboard) while it dries.
  • Do not walk on it or put anything on it for 3 to 4 days.
  • No water for 3 days.
  • Hardening is complete after 7 days at 20 °C.

Mistakes to avoid

  • Sanding too fine between the A coats: a fine abrasive "burns" the surface and darkens the shade.
  • A stainless steel trowel for the B coat: it leaves grey marks.
  • Poor vacuuming before the varnish: a grain of sand leaves a tiny hole at the slightest wear.
  • Varnishing too early: wait 24 h after the B coat.

Getting help

To get a feel for it, we offer training courses. Your stockist will help you plan the job. For a walk-in shower, a trained applicator is recommended.

What surfaces can microtopping go on?

SubstrateApplicationMain condition
Cement screed or slabSuitableSound, dry, stable and prepared substrate
Underfloor heatingSuitable, following the protocolHeating run beforehand, stability, movement joints respected
Existing tilesPossible after inspectionAdhesion, stability, sanding and the right primer
Plasterboard on wallsSuitableRigid boards, treated joints and preparation
Wood or wood-based panelsSuitable except solid woodDimensional stability and sound assembly (screwed and glued)
Terracotta or damp substrateNot recommended on substrates soaked deep with old oil or wax. Max. moisture 5%Surface and moisture check required beforehand

Frequently asked questions

How long does it take to apply microtopping?

4 to 5 days on site: primer, three coats of microtopping with their sanding, then two coats of varnish. Allow 7 days before normal use.

Can I apply microtopping myself?

Yes. The product is ready to use and does not dry out in the tub. Do a test before the real job; for a walk-in shower, a trained applicator is recommended.

How many coats do I need?

One primer, three coats of microtopping (two A coats and one B coat), then two coats of varnish.

What tools do I need?

A sander, a vacuum cleaner, a roller, a trowel or a spatula for the A coats, a plastic smoothing spatula for the B coat, and a paint mixer for the varnish.

When can I walk on microtopping?

Not before 3 to 4 days, and no water for 3 days. Full hardening takes 7 days at 20 °C.